An EN 10204 3.1 inspection certificate (often called an MTC or mill test certificate) is the document that proves the fittings you receive are made from the material you ordered. It is only useful if someone actually checks it against the order and against the parts. This guide explains what each section of a 3.1 certificate tells you and how to cross-check it, line by line, when you receive a fittings shipment.
What an EN 10204 3.1 Certificate Is
EN 10204 defines the types of inspection document for metallic products. A type 3.1 certificate is issued by the manufacturer and confirms that the products comply with the order, with test results from specific inspection — tests carried out on the actual heat or batch being supplied, not typical values. It is validated by the manufacturer's authorised inspection representative, who must be independent of the manufacturing department.
- Type 2.1 / 2.2: declaration of compliance, with or without non-specific test results. Usually not acceptable for pressure piping.
- Type 3.1: specific test results, validated by the manufacturer's independent inspection representative. The normal requirement for ASTM / ASME fittings and flanges.
- Type 3.2: as 3.1, but also validated by the purchaser's inspector or a third-party inspection agency named in the order.
The Sections of a 3.1 Certificate
Layouts differ between mills and fitting manufacturers, but a complete certificate contains the same blocks of information:
- Header: manufacturer name and address, certificate number, date of issue and the words "EN 10204 3.1".
- Order reference: your purchase order number and line item, or the supplier's sales order that can be traced to it.
- Product description: fitting type, size, schedule or pressure class, end connection and quantity.
- Specification and grade: for example ASTM A403 WP316L, ASTM A234 WPB or ASTM A182 F304L, ideally with the dimensional standard (ASME B16.9, B16.11) and edition year.
- Heat number (and lot or batch number): the identifier that links the certificate to the material and to the marking on each fitting.
- Chemical analysis: measured percentages for each element required by the grade.
- Mechanical test results: tensile strength, yield strength, elongation, and where required reduction of area, hardness and impact (Charpy) values with test temperature.
- Heat treatment: condition such as solution annealed, normalised, or quenched and tempered, with temperatures where the specification requires them.
- Other tests: NDT, intergranular corrosion, PMI, hydrostatic test, dimensional and visual inspection, as ordered.
- Statement of compliance and validation: a declaration that the products meet the order, signed or stamped by the authorised inspection representative.
Step-by-Step: Checking the Certificate Against Your Order
1. Match the certificate to the purchase order
Confirm the PO number, line items, sizes and quantities. A certificate that cannot be traced to your order — or that covers a different size range — is a document problem to resolve before the material is accepted.
2. Check the specification, grade and edition
The grade on the certificate must be exactly the grade ordered. WP316 is not WP316L; WPB is not WPC. If your order allows dual certification (for example WP316/316L), the certificate should state both grades and the results should satisfy both. If the project specifies a particular edition of the standard, check the year shown.
3. Trace the heat number to the fittings
Every fitting should be marked with the manufacturer's identification, the grade, size and the heat number or a heat code. Pick fittings from each size and check that their marking matches a heat number on the certificate. If one certificate covers several heats, each heat must have its own chemistry and test results.
4. Compare chemistry with the grade limits
Check each element against the limits in the material specification. For low-carbon grades, look first at carbon (0.030% maximum for 304L / 316L). For stabilised grades such as 321, check the titanium-to-carbon ratio. For alloy steel grades such as WP11 or WP22, check chromium and molybdenum.
5. Compare mechanical results with the minimums
Tensile, yield and elongation must meet the specification minimums (and tensile must not exceed a maximum where one applies). If impact testing was ordered — common for low-temperature service such as WPL6 — check that the test temperature and the absorbed energy meet the order.
6. Confirm heat treatment and supplementary tests
The heat treatment condition must match what the specification requires for the grade. Any supplementary requirement written into your order — NACE MR0175 hardness limits, intergranular corrosion testing, 100% PMI, radiography of welded fittings — should appear with its result.
7. Check validation and certificate type
The document must be identified as EN 10204 3.1 (or 3.2 if ordered) and validated by the manufacturer's authorised inspection representative. For a 3.2 certificate, the third-party or purchaser's inspector must also have signed.
Common Problems to Look For
- Typical or "guaranteed" values instead of actual test results — that is not a 3.1 certificate.
- A raw-material certificate (pipe or plate mill) supplied without the fitting manufacturer's certificate, when the fittings were formed and heat treated by a different company.
- Heat numbers on the parts that do not appear on any certificate in the shipment.
- Grade or size on the certificate different from the PO.
- Missing results for tests that were specified in the order.
- Edited, illegible or incomplete scans. Ask for a clean copy from the issuer.
What to Request in Your RFQ
Avoid disputes at receipt by stating document requirements up front: the certificate type (3.1 or 3.2), the inspection agency for 3.2, supplementary tests, whether dual certification is acceptable, and whether you need the raw-material certificate in addition to the fitting manufacturer's certificate. See our FAQs for more on documentation, or browse our pipe fittings and flanges.
Ask About Certificates for Your Order